Exhibitor Action Pack
SAMPLE-JIS-FALL-2026

JIS Fall 2026
Exhibitor Action Dossier

Representative selected vendor deadlines, freight dates, cabinet-order dates, decisions, risks, and exceptions.

Demonstration only. The exhibitor identity and booth profile are fictional. This intentionally incomplete sample is not affiliated with or endorsed by JIS, RX, Expo Convention Contractors, or any organizer or contractor. It must not be used to operate a real booth.
Customer
Northstar Instruments (Fictional)
Source snapshot
2026-07-28
Control items
10
Critical items
5

Dossier summary

Show datesOctober 16–19, 2026
Booth profileFictional 10×20 inline booth; booth number and planned services not supplied
Conditional items9; customer confirmation is required before they are treated as applicable.
CoverageRepresentative selected vendor deadlines, freight dates, cabinet-order dates, decisions, risks, and exceptions.

Action register

ID / applicabilityDateCategoryAction and decisionOwnerPriorityRiskSource
ACT-001
Conditional
2026-08-28
29 days remaining
Booth packageDecide whether the turnkey booth package is required and submit the applicable order by the discount date.

Decision: Confirm whether the standard booth package already covers planned furnishings.
Event LeadHighLater pricing or reduced preparation timeSRC-01
Turnkey Booth Order Form — Discount Date
ACT-002
Conditional
2026-08-28
29 days remaining
GraphicsFinalize whether custom graphics are required and submit the applicable graphics order by the listed discount date.

Decision: Approve final artwork, dimensions, and budget.
MarketingHighLate fee, production delay, or unavailable graphicsSRC-01
Graphics Order Form — Discount Date
ACT-003
Conditional
2026-09-14
46 days remaining
ElectricalDetermine booth power requirements and submit the electrical order by the discount date.

Decision: List every powered device and required placement.
Event LeadCriticalHigher cost or inability to support planned equipmentSRC-01
Electrical Order Form — Discount Date
ACT-004
Conditional
2026-09-18
50 days remaining
Exhibitor-appointed contractorComplete the EAC information and fee process when an outside contractor will work in the booth.

Decision: Confirm whether any nonofficial contractor will perform installation or dismantling.
OperationsCriticalContractor access or approval failureSRC-01
EAC Information and Fees — Discount Date
ACT-005
Conditional
2026-09-25
57 days remaining
Hanging signsSubmit the hanging-sign or banner order when overhead signage is planned.

Decision: Confirm sign dimensions, weight, rigging need, and approved artwork.
MarketingHighLate pricing or inability to install planned signageSRC-01
Hanging Signs and Banners — Discount Date
ACT-006
Conditional
2026-09-25
57 days remaining
Cabinet graphicsSubmit orders, payment, and ready-to-print cabinet graphics by the discount deadline when custom cabinet graphics are required.

Decision: Confirm cabinet selection and provide final production-ready files.
MarketingHighLoss of discount or production delaySRC-03
PDF page 2 — cabinet-graphics discount deadline
ACT-007
Conditional
2026-10-02
64 days remaining
Advance freightEnsure advance warehouse shipments arrive by the material-handling deadline when using advance shipping.

Decision: Select advance warehouse or direct-to-show shipping and book the carrier.
LogisticsCriticalAdditional 25% late-handling surchargeSRC-02
PDF page 1 — advance-shipment deadline
ACT-008
Conditional
2026-10-12
74 days remaining
Cabinet order pricingComplete any remaining eligible cabinet or shelving orders before the stated standard-pricing deadline.

Decision: Confirm no outstanding furniture or cabinet requirements remain.
Event LeadMediumShow-site pricing begins after the standard deadlineSRC-03
PDF page 2 — standard deadline
ACT-009
Conditional
2026-10-15
77 days remaining
Direct freightDo not schedule direct-to-show freight to arrive before the source-stated acceptance date.

Decision: Confirm carrier appointment and exact delivery address.
LogisticsCriticalShipment refusal, delay, or rehandlingSRC-02
PDF page 1 — direct shipments not accepted before date
ACT-010
Required
2026-10-16
78 days remaining
Show openingConfirm booth staffing, materials, access, and required services are ready for the first show day.

Decision: Complete internal go/no-go review.
Event LeadCriticalIncomplete booth readiness at show openingSRC-02
PDF page 1 — show dates October 16–19, 2026

Exception and missing-information register

IDSeverityIssueRequired resolution
EXC-001CriticalThe public sample source set does not establish the fictional exhibitor's booth number, dimensions, included furnishings, or power draw.Customer must supply the booth profile and contract-specific facts before production.
EXC-002HighSeveral services are conditional; the public source does not establish whether the fictional exhibitor needs them.Customer must confirm planned services during intake.
EXC-003HighThe organizer tells exhibitors to verify dates against underlying forms and makes the exhibitor responsible for accuracy.Paid dossiers must use the complete customer-supplied forms as controlling sources and preserve a snapshot.
EXC-004MediumThe sample does not cover every vendor, rule, move-in instruction, insurance item, or later revision.Every paid dossier must list its exact source inventory and coverage boundary.

Quality controls

Source map

SRC-01 — JIS Fall 2026 Exhibitor Manual — Vendor Forms and Deadlines
Publisher: JIS / RX · Snapshot: 2026-07-28
Locator: Vendor Forms and Deadlines section
https://www.jisshow.com/fall/en-us/for-exhibitors/exhibitor-resources/exhibitor-manual.html
SRC-02 — JIS Fall 2026 Material Handling Authorization
Publisher: Expo Convention Contractors · Snapshot: 2026-07-28
Locator: PDF page 1
https://www.jisshow.com/content/dam/sitebuilder/rna/operations/show-specific-documents/jis-fall/2026/JIS_FALL_26_Material%20Handling.pdf.coredownload.781348453.pdf
SRC-03 — JIS Fall 2026 Cabinet and Shelving Order Form
Publisher: Expo Convention Contractors · Snapshot: 2026-07-28
Locator: PDF pages 2–3
https://www.jisshow.com/content/dam/sitebuilder/rna/operations/show-specific-documents/jis-fall/2026/JIS_FALL_26_Cabinet_Shelving%20Order%20Form.pdf.coredownload.782152294.pdf

Coverage and exclusions

This sample is a document-control artifact, not event management or legal, safety, insurance, labor, shipping, rigging, customs, tax, engineering, or vendor-selection advice. ShowDossier does not access portals, place orders, pay vendors, contact organizers, monitor later changes, or guarantee that supplied sources are complete or unchanged.